kanban 설정 주요 t-code

sapjoy 2018.12.27 10:08 조회 수 : 742

kanban 설정 주요 t-code

 

PK13N

PK12N - KANBAN STATUS CHANGE

 

KANBAN is having two master data.

1.    Control cycle

2.    Supply area

First of all supply area will be created with storage location and responsible person.

T code PK05. Put the plant and create new entry.

Put storage location and responsible person and save the data.

Go to MMSC

Exclude the storage location from planning(as this is not required to plan through MRP). We can exclude the storage location from customizing also. In this case all the material in the storage location will be excluded for planning.

Now the control cycle has to be created.

T code PK01

Put material, plant, supply area and select classic KANBAN.

Put no of KANBAN (means no of  bins), No of KANBAN quantity and maximum empty allowed.

Select production type also (inhouse/external).

This can be done through control cycle maintenance also. T code PKMC. To create new click on  

Now check MD04 screen

Total stock is 63 and is excluded from MRP. This stock will be consumed in subsequent stage(in next stage)

Now check the status of the KANBAN bin. T code PK13N

Here three bins are full and two bins are in Wait status. Click    to see the legends.

Two important status of KANBAN is.

If Bins are made full- GR will be done

If Bins are made empty-Procurement proposal will be created (NOT GI WILL BE DONE)

GI is being done through backflush.

In actual situation bins are being scanned through RF device and scanning is being done one the Bins are empty or Full.

But here we will do through this tab.

Let’s select one bin and make it empty by 

One KANBAN processed and Bin became RED. This means Bin is empty.

Now check MD04. One Production order created (as empty means one proposal will be created).

Make another Bin empty is same process and see MD04 screen.

Release both the order. The order type of KANBAN is PP05.

Double click on the Bin and you can see the details with order created.

Check the stock in MMBE

Stock is 63. Now select one empty Bin in make it Full 

The Bin became green.

Check the stock

Its become 70 unrestricted. Hence 7 nos GR is happened.

Repeat the process and check the qty .More 7 no GR happened

Check MD04. No proposal exist (for all orders GR happened).

Few more useful T codes

PK11: Plant overview.

PK18: For each material production order, DOC no on which the production order got posted can be seen. Status of KANBAN container will be displays also.

PK31: Error in KANBAN can be checked. Select any error line and click on Bell. You can change the error status.

PK09: KANBAN can be locked (when the KANBAN is not is used/Bin is damaged).

 

SOURCE : https://blogs.sap.com/2014/01/06/kanban-execution-step-by-step-approach/

번호 제목 글쓴이 날짜 조회 수
237 과거 MRP Element 삭제하는 방법 킥복서 2020.11.30 363
236 PP_ 2개 공정 동시 시작 설정 file PP_MRP_Controller 2020.09.11 664
235 Usage decision 저장 후, 동작하는 user exit 문의 HANAMANA 2020.08.26 215
234 생산오더 Delivery Completed SAPSAP 2020.08.25 756
233 [백로그] 실적처리 시 자재 출고(투입) 오류 - 백로그 발생 [2] file 아좀더 2020.06.16 1566
232 pp - mrp 실행시 Delivery Schedules 옵션은 언제 쓰는건인가요? [2] sapabaper 2020.05.04 540
231 MRP2 VIEW 조달유형, 특별조달유형 좀 알려주세요..ㅠ [2] sapabaper 2020.04.23 2247
230 sap mrp2 view co-product 는 언제 체크합니까? [2] sapabaper 2020.04.20 798
229 생산오더에서 라우팅 테이블 [1] sapabaper 2020.04.03 989
228 생산오더 확정 프로세스 문의 SAP유망주 2020.03.04 1018
227 라우팅 삭제된 그룹카운트 사용하는 법 아시는분.. [1] 짱똘리안 2019.11.26 499
226 BOM 관련 문의 드립니다. 공100 2019.08.28 943
225 pp 점검 리스트? sap는어려워 2019.03.18 633
224 I/O error for text AUFK & MATK EN - 계획오더 생산어더 convert sapjoy 2019.03.14 398
223 PP 모듈 배치관리 해제 [1] 문사장님 2019.02.27 669
222 Producion Order status 질문 [2] sap는어려워 2019.01.31 2206
221 PP 원자재 추가 투입 관련 문의드립니다 ㅠ [2] 아밥자 2019.01.09 769
220 생산오더 실적 처리시 자재문서 관련 테이블 연관도.. 어떻게..ㅠ [2] 아밥자 2019.01.04 1513
» kanban 설정 주요 t-code [1] sapjoy 2018.12.27 742
218 BOM 삭제시 삭제 취소 가능한가요? devilston 2018.12.07 676