Regarding SPRO settings, creating REM Profile in T Code OSP2---> here you have to make the seetings
related to Costing whether you want to use Standard Cost estimate or using the preliminary costing data
from the product cost collector for backflushing,whether you want to execute the correction in dialog mode
mandatory or optional,whether you want to create Post processing records individually(you can see the
error good's movement's list in COGI) or cumulated one (you will be finding only in MF45,46 or MF47) and
the planned order reduction and the Good's movements.
Goods issue 261 Goods issue/reversal 262
Goods receipt 131 Goods receipt/reversal 132
Scrap 551 Scrap/reversal 552
By-product 531 By-product/reversal 532
The sequence in REM is
1.MM01-material creation.(MM01- FERT,HALB,ROH Types),in MRP4 view you have to include the REM
allowed indicator and the REM profile assigned for all the Inhouse manufactured items.
2.CS01 - BOM creation.(CS01- Create BOM's for your FERT & HALB).
3.Work centre creation.(CR01)
4.Rate routing.(CA21 - For In house manufactured HALB & FERT's).
5.Creating production version to link BOM & Rate routing.(Using MM02 - MRP4view or else C223).
6.Creations of product cost collector using production version.(KKF6N,KKF6M).
7.Cost rollup & Release using CK40N.
8.Demand values (MD61 - Planned Independent Requirements),
9.MRP Run(MD02 - Single Item Multi Level),
10.Planned orders generated(Checked in MD04).
11.Pull List MF60(Using Planned orders to stage the material).
12.You can get the reservation number's in MB25,made for 311 movement,using MF65,you can transfer the
materials agianst the reservation number.
13.MFBF(Assembly Backflush - 261 & 131,Component Backflush - 261,Activity Backflush for extra time
spent for the operations).
14.Settlement - KK87-month end if any variance.
In addition to the above Planning table(MF50) can be used for adjusting the values as per to the capacity
availability.
댓글 0
번호 | 제목 | 글쓴이 | 날짜 | 조회 수 |
---|---|---|---|---|
448 | 숫자입력 체크(Numeric character check) [1] | 양키(이경환) | 2014.01.28 | 20001 |
447 | 인터널 테이블 라인수 lines [8] | sapjoy | 2014.01.20 | 17685 |
446 | TRY와 SQL [2] | sapjoy | 2013.12.05 | 5984 |
445 | SAP 버퍼를 다시 설정하는 방법 | Wise 멘토 | 2013.10.05 | 7522 |
444 | debug 시 문장 skip 요령 [36] | 하마대왕 | 2013.10.04 | 7037 |
443 | SAP GUI 730 ALV Grid 느림 현상(해결방법) [3] | Dave | 2013.09.27 | 8935 |
442 | TYPE-1 프로그램에서 실행버튼 없애기 [1] | 아밥뽀 | 2013.09.24 | 9192 |
441 | sap 메뉴에서 표준 매뉴 전환 [1] | selection장 | 2013.09.13 | 9482 |
440 | 요약파일1 [7] | 밤의화신 | 2013.09.12 | 8059 |
439 | ABAP 교육 [13] | 밤의화신 | 2013.09.12 | 8385 |
438 | ABAP 교육 [9] | 밤의화신 | 2013.09.12 | 7411 |
437 | ABAP 교육 [6] | 밤의화신 | 2013.09.12 | 7222 |
436 | ABAP 교육 [6] | 밤의화신 | 2013.09.12 | 7286 |
435 | ABAP 교육 [12] | 밤의화신 | 2013.09.12 | 7303 |
434 | ABAP 교육 [32] | 밤의화신 | 2013.09.12 | 8514 |
433 | ABAP 교육 [13] | 밤의화신 | 2013.09.12 | 8516 |
432 | REM PROCESS2 [1] | 밤의화신 | 2013.09.11 | 4539 |
» | REM PROCESS1 | 밤의화신 | 2013.09.11 | 5434 |
430 | REM TABLE3 | 밤의화신 | 2013.09.11 | 2670 |
429 | REM TABLE2 | 밤의화신 | 2013.09.11 | 2829 |