안녕하세요.
KSPP 에서 엑티비티 전송시에 전체가 아닌 부분만 전송되고 있습니다.
내역은 아래와 같은데 해결 할수 있는 방법이 있는지 문의 드립니다.
Partial transfer only of activity quantities to plan/SOP order 223291355.
Message no. KP602
Diagnosis
During termination of the plan or SOP order 223291355, start date 2021.12.07 and end date 2022.02.01 were found.
This is not entirely within the transfer timeframe of 012 - 012/2021 for activity quantities in Cost Center Accounting (CO-CCA).
This problem occurs when the logistical planning process is made on a basis other than monthly. Here, plan or SOP orders were created for periods only partially in the start or ending periods.
Example
Weekly logistical planning results in plan orders created for the week of 30 Dec 1996 to 3 Jan 1997. During transfer of activity quantities for 1997 to CO-CCA, the plan order quantities can only be taken partially into account. The 1997 quantities are included, while those in 1996 are not transferred.
System Response
Activity quantities for plan or SOP order 223291355 are transferred only partially. Those not transferred are identified separately in the results list.
Procedure
Check whether further reconciliation between CO-CCA and long-term, requirements, and preliminary planning is necessary.
PP 계획오더의 일정계획이 CCA의 계획연도 바깥에 있기 때문입니다.
T-CODE: MS12 같은 화면에 들어가셔서 해당 오더 번호 223291355를 넣으시고 상단의 '계획오더 일정계획' 버튼을 눌러보세요.
'세부일정계획' 탭에서 작업 시작일과 종료일이 보일 텐데 연도가 다른 행이 있을 겁니다.
아마 22년으로 수행하셨을텐데 일정계획상 21년 12월의 액티비티 소요량은 제외하고 부분적으로 전송되었을 거고요.
일단은 KSPP의 옵션 중 '기간조정실행'에 체크하고 돌리시면 모두 포함되게끔 바뀌긴 합니다.
제가 해당 옵션을 체크했을 경우와 체크하지 않았을 경우의 예시를 작성한 게 있는데 아래 참고해보세요
https://ckm3.tistory.com/21